Estimate Bug

We have case in our on-demand system. First estimate was 2 hours, later developer changed estimate to 4, 6 hours and 1 day at the end. But FogBugz use 6 hours estimate as original estimate instead of 2 hours.
Screenshot: http://www.martyanov.ru/wp-content/uploads/2007/12/fogbugz_bug.PNG
Denis Martyanov Send private email
Tuesday, December 11, 2007
 
 
I don't work for Fogbugz, so don't treat this as an "official" answer. But how I think it works is that the original estimate is only saved permanently (i.e. locked down) at the point someone first starts working on it.
Greg Whitfield Send private email
Tuesday, December 11, 2007
 
 
Greg's got it right.  We're working on more documentation for EBS to explain things like this.
Eric Nehrlich Send private email
Tuesday, December 11, 2007
 
 