Updating current estimate also updates original estimate.

When I update the current estimate of an item and then go to check the original estimate for that item the values for 'Estimate(original)' and 'Estimate(current)' are always identical.

This is true whether I view the values in a list through the FogBugz UI or through the FB web API. This was checked against a FB On Demand account.
Stephen Martin Send private email
Wednesday, May 27, 2009
 
 
Have you done any work on the case?
Jacob Krall Send private email
Wednesday, May 27, 2009
 
 
After I noticed this on one item I updated a few more at random. I just went back and checked and by a weird coincidence all of the ones I picked had no work done.

I don't need to update estimates very often so I've never noticed this before and I couldn't find a mention of it in the docs or this group. I don't really agree with this design decision but as long as I know what's going on I can handle it.

Thanks.
Stephen Martin Send private email
Wednesday, May 27, 2009
 
 

This topic is archived. No further replies will be accepted.